Working closely with our client, our skilled site team overcame the complexities of installing a 49m DN150 hashtag clay hashtag gravity hashtag pipeline beneath a live road and into a roundabout.
Key highlights:
* 49m drive successfully completed.
* DN150 clay gravity pipeline installation.
* Minimal disruption to traffic flow.
* Strong collaboration with our client.
We’re proud to contribute to the development of robust infrastructure in the region. A big thank you to everyone involved!
If you would like to benefit from our experience on you next hashtag trenchless installation Get in touch with our team today: 01226 785722