The team has been putting in serious graft this weekend! On Friday, we set up the rig pilot, kicked off the installation of the 219mm casing and augers yesterday, and wrapped it up today—retracting all 40m of augers. Now, we’re all set to push in the DN150 Naylor Industries Denlok clay pipe first thing in the morning.
Fantastic progress, team!